How Design Changes Should Be Handled in the DfS Register

Good practice
In brief

A design change that affects risk — including a substituted construction method, revised temporary works, or altered access arrangement — should trigger a follow-up DfS review, and the Register should be updated to reflect the new position, not left describing a superseded design.

Direct answer

Construction rarely proceeds exactly as detailed-designed. When a change affects a previously reviewed design risk, the DfS process is meant to catch up with it — not leave the Register describing a design that no longer matches what is being built.

What should trigger a review

  • A substituted construction method or sequence that changes exposure to a previously identified risk
  • A revised or newly introduced temporary works scheme
  • A change to site access, egress or working-at-height arrangements
  • A value-engineering or buildability change to a structural or façade element
  • A change in scope that introduces a new foreseeable risk not previously considered

Updating the Register

1

Flag the change

Designer, Contractor or DfSP identifies that a change may affect a previously reviewed risk.

2

Follow-up review

DfSP convenes a follow-up review with the relevant parties for the affected scope.

3

Update the record

Design Risk Record and residual-risk entries updated to reflect the new design.

4

Re-communicate

Updated Register reissued so the Contractor and design team are working from current information.

See our main page on the DfS Register → and the full DfS process across project stages →.