In brief

Core attendance is the Developer (or its representative), the relevant Designers for the stage under review, and the Contractor once construction-stage risks are in scope. Specialist and temporary works designers should attend directly whenever their design creates or controls material risk.

Direct answer

A DfS review is only as good as the people who can actually answer the questions it raises. Sending a representative who was not involved in the specific design under discussion tends to produce vaguer, less useful review outcomes.

Typical attendees

Who typically attends each type of DfS review
AttendeeWhy they are there
Developer / representativeOwns the decision to accept, defer or reject proposed design changes
Architect / permanent works designerCan explain and adjust the design under discussion
Specialist designers (M&E, façade, etc.)Own risks specific to their systems
Temporary works designerOwns risks arising from formwork, falsework, shoring or similar temporary structures
Main contractorBrings construction-method knowledge once appointed, especially pre-construction onward
DfSPFacilitates the meeting and records outcomes

When temporary works designers must attend

Professional boundary

Designers engaged by the Contractor, including temporary works designers, should participate directly in a DfS review when their designs create or control material risks — not be represented secondhand by the main Contractor.

See why temporary works designers " "should join relevant DfS reviews →.

Official references

  • GuidanceWSH Council, Workplace Safety and Health Guidelines — Design for Safety — official source →