What Happens During a DfS Review Meeting?

Process
In brief

A DfS review meeting brings the Developer, Designers and Contractor together to identify foreseeable design risks at a specific project stage, decide how to eliminate or reduce them, and record the outcome as a Design Risk Record.

Direct answer

The meeting works through the current design with the people who created it, asking a structured question: who could foreseeably be harmed by this design, at what point in the building's life, and can that risk be removed or reduced through a design change?

Typical flow

1

Briefing

DfSP briefs attendees on the stage's DfS objectives and prior open items.

2

Walk-through

Design reviewed element by element for foreseeable risk to construction, use, maintenance or demolition.

3

Discussion

Team discusses elimination first, then reduction at source, then collective before individual controls.

4

Recording

Hazards transferred to Design Risk Records; decisions and residual risks captured in minutes.

5

Follow-up

DfSP sets or confirms actions and, where needed, schedules a follow-up review.

Who is considered

Reviews are meant to consider people who carry out or are affected by construction work, people for whom the finished structure is a workplace — including those who later clean or maintain it — and people affected by its eventual demolition. This is broader than the construction phase alone.

See who should attend a DfS review meeting → and the full DfS process across project stages →.