Clarification
In brief

A DfS review addresses risk arising from design decisions, before construction methods are finalised. A risk assessment and safe work procedure address how a specific task will actually be carried out on site. They are related, sequential, and not interchangeable.

Direct answer

Confusing these three is one of the more common gaps we see. A DfS review does not replace a Contractor's obligation to prepare risk assessments and safe work procedures for site activities, and a risk assessment does not retroactively fix a design that created an avoidable hazard in the first place.

Side by side

DfS review, risk assessment and safe work procedure compared
DfS reviewRisk assessmentSafe work procedure
Owned byFacilitated by DfSP; input from Developer, Designers, ContractorContractorContractor
FocusRisk arising from design decisionsRisk arising from a specific work activityHow that activity is to be carried out safely
TimingConcept through pre-construction, plus follow-upsBefore the activity is carried outBefore the activity is carried out
OutputDesign Risk Record, DfS Register entryRisk assessment documentWritten procedure / method statement

How they connect

A residual design risk recorded through DfS review often becomes an input to the Contractor's risk assessment — for example, a design decision that leaves work-at-height exposure should be flagged so the Contractor's risk assessment and safe work procedure address it directly on site. The DfS Register is the bridge that should carry that information from design into site planning.

Official references

  • GuidanceWSH Council, Workplace Safety and Health Guidelines — Design for Safety — official source →
  • RegulatorMinistry of Manpower, Workplace Safety and Health circulars — official source →